In the V8 TRACC Platform, you continue to update an existing assessment over time by clicking the Assess button and changing your responses. This is a key change in the assessment process - you no longer need to 'right-click create' or 'right-click copy' which is the case in the V7 Platform.
When you change responses this will automatically update your assessment history by recording the changes captured that day, which includes any criteria responses captured via your plan.
This approach preserves the record of maturity improvement over time as it prevents people mistakenly updating an assessment you completed a long time ago.
If you'd like to hide the previous responses for an assessment, you can:
A. Hide verified responses by turning off the View Verified Responses toggle
B. Hide the latest responses by turning off the Reveal Latest Responses toggle
Note: This is merely a visual aid which hides the latest responses. It does not remove those responses from the assessment.